The Army detonated a stockpile of unstable lead azide explosives in southeast Iowa on Wednesday in a blast that was expected to spread lead dust for miles.
The detonation at the Iowa Army Ammunition Plant in Middletown was intended to eliminate 68 drums of deteriorating, toxic lead azide — about 9,700 pounds. The Army said the material had become “recrystallized” inside and outside the drums, putting it at risk of a spontaneous explosion and making it unsafe to move.
NBC affiliate KWQC of Iowa filmed the detonation from a location in Danville, about 4 miles north of the plant.
Just after 9 a.m. local time, the camera feed captured two blasts of gray and white smoke that appeared to dissipate after about 30 seconds. Reporter Cyle Dickens said he felt a “percussion” from the explosion and a shock wave that traveled across a farm field toward him.

Linda Ross, who lives about a mile southwest of the site, said she felt “very little shaking” in the moments after the blast. “Two short boom boom sounds. Dog started barking. That’s about it,” she said.
Still, Ross added, it was “unnerving.”
“We will stay inside today,” she said.
A host of state and federal leaders sought to offer the public assurances after the blast, including President Donald Trump and Iowa Gov. Kim Reynolds. However, independent experts have said it will take some time to determine how much lead was deposited and what the risks to nearby communities could be.
Maj. Gen. Eric Shirley, the commanding general of the U.S. Army Sustainment Command that led the U.S. Army-controlled detonation, said it had exceeded his expectations.
“I believe absolutely that we reduced as close to zero as is absolutely humanly possible the risk to the health and safety of the people of Middletown,” Shirley said in a video message broadcast by the Army. “As we saw in the immediate aftermath through overhead coverage, all of the lead azide barrels were definitively removed. There was no secondary explosions. ... There was no infrastructure damage in or around our installation.”

Shirley attributed the visible clouds that emanated from the blast site to the foam solution the Army sprayed there.
Robert Cekada, director of the Bureau of Alcohol, Tobacco, Firearms and Explosives, said in the video that military personnel had successfully driven the explosion “into the ground,” minimizing pollution.
The Environmental Protection Agency, which approved the Army’s permit to detonate, said air quality monitors were reporting “ZERO detection of airborne lead throughout the region.”

00:33
However, previous modeling suggested it would take several hours for the dust plume to disperse. Multiple experts agreed that it’s too early to make conclusions about lead pollution levels.
Andrew Whelton, a professor of civil, environmental and ecological engineering at Purdue University in Indiana, said that although the EPA’s real-time air monitoring data suggests some potentially promising results, “physical analysis” of samples is necessary.
“Multiple lines of evidence are needed,” he said.
Still, Whelton said that in video footage, the blast appeared smaller than what he had expected, given the Army’s descriptions ahead of time.
“It’s possible that if there is a lead release, it is more contained to the detonation site than it could have been,” he said.

Before the explosion, the Army had called for evacuations in Middletown and a 5-mile zone to the southwest of the ammunition plant.
Soldiers went door to door Tuesday afternoon to notify residents that they should evacuate. The Federal Emergency Management Agency is providing short-term hotel lodging to those in the evacuation zone through Friday.
Based on Wednesday’s expected weather conditions, Army projections indicated the cloud of lead dust could travel some 100 miles southwest and cross into northeastern Missouri.
The plan prompted widespread fear and anger among local residents in the days before the detonation, with many saying they did not receive enough warning. People in the potential path of the plume scrambled to change Thanksgiving plans, tape windows, cover gardens, buy cleaning supplies and, in some places, get their families out of town.
Jill Holler, who has a family farm about 20 miles west of Middletown, said she spent Sunday night rushing to take soil samples for future comparisons of lead concentrations.
“I was down in the dark getting the soil samples, and it’s just frustrating,” she said.
Lead is a potent neurotoxin and no amount of exposure is safe. It poses the biggest health threat to children. Exposure is associated with learning disabilities, reproductive health problems, mental health issues and increased risk of hearing loss, among other effects.
Once deposited on surfaces or in soil, lead particles can remain there forever unless physically removed.
Army officials have maintained that it was safer to detonate the chemicals in a controlled manner, with mitigation measures in place, than risk a surprise blast. Before the detonation, they described a range of mitigation strategies intended to keep as much lead dust as possible within the ammunition plant.
That included two stories of “HESCO” barriers — modular, collapsible structures filled with sand — built around the detonation site and a plan to spray water during the explosion to catch small particles. Officials also said aqueous foam blocks, gel blocks and two “water walls” made of four 16,000-gallon water tanks each would help absorb the blast.
In a statement after the detonation on Wednesday, Iowa Governor-elect Rob Sand said that although more testing needs to be done, federal officials had told him everything had gone well.
Still, he added, “the lead-up to the detonation should never have been so chaotic and unclear.”


According to emergency permitting documents submitted to the EPA, the Army expected the blast to leave a crater about 38 feet wide and 5 feet deep.
The Army said in a release Tuesday that after the detonation, environmental monitoring teams would follow the plume’s path “to collect soil, surface-water, and surface-wipe samples to verify lead levels.”
If any residential properties are found to exceed a certain threshold of lead contamination — 200 parts per million — the Army said, “remediation teams will remove affected soil, clean surfaces, and restore the property at complete government expense.”
It offered few specifics, however, about how or when such testing would be conducted — or the process or timeline for any government-led remediation work.
Whelton said that even the Army’s emergency permit did not describe those plans in detail.
“Based on the document I reviewed, there is no plan for applying an evidence-based approach to determine if people’s homes, schools, and businesses are safe after the detonation,” he said on Tuesday.
Peter Thorne, a pulmonary toxicologist and environmental health specialist with the University of Iowa’s College of Public Health, said that scientists planned to conduct independent monitoring of the plume.
“We have monitoring equipment out there that’s going to tell us the extent of lead that’s became airborne and moved with the wind,” he said Tuesday. “Our models will be able to tell us how much lead is depositing on soil and on playground equipment and so forth. And from that, we can make some estimates of what the degree of danger is associated with this exposure.”
The nation’s stockpile of lead azide — once used to make bomb triggers but mostly phased out of the process about 15 years ago — was moved to the ammunition plant in 2009, officials have said. Cekada said Tuesday that the chemicals were known even at that time to pose a problem.
Thorne questioned how these explosives were allowed to become so dangerous over so many years.
“It should have been dealt with in the past, and now it’s become a crisis,” he said.